Three construction companies were fined last week over the incident, which took place during construction of the Sleaford Renewable Energy plant on 14th February 2013.
Michael Doyle, a 49-year-old employee of Derby-based Shaw Group UK Ltd, was crushed by a falling 4.5-tonne section of conveyor that overturned during installation. He suffered four cracked vertebrae, broken ribs, a punctured lung and broken ankle. He has not returned to work since.
Lincoln Magistrates鈥 Court heard that Shaw Group UK Ltd had been subcontracted to install a boiler and associated equipment , including a conveyor system to carry large straw bales, by Danish company Burmeister & Wain Energy (BWE).
BWE was one of two Danish companies, the other being Burmeister & Wain Scandinavian Contractor (BWSC), that had formed a consortium to design and build the centre, which burns straw and wood to create electricity and also to provide heat for some local authority buildings.
Shaw Group UK Ltd had already lifted three conveyor sections on to a slope leading up to the boiler by craning them on to a platform at the bottom of the slope. Skates were bolted to the front and rear legs which helped keep the section of conveyor on rails as it was dragged up the slope by manual winches set up at the top.
To fix the sections of conveyor in place workers needed to remove the skates and use jacks to raise the legs enough to take the skates off, and then lower the legs down onto the rail. This was carried out successfully on the first three sections but as the jacks were released on the lower legs of the fourth and final section, one side lowered faster than the other and the conveyor swung towards two workers before violently swinging the other way and turning on its side, trapping Mr Doyle underneath.
聽A Health & Safety Executive (HSE) investigation identified safety failings by all three companies.
Shaw Group UK Ltd had produced a risk assessment and a plan for the installation but it did not consider removal of the skates from the legs of the conveyor sections or the manual winching of the load up the slope. The document had been sent to BWE for checking but the company did not pick up on the omission.
The lifting operation using jacks was not carried out safely and none of the three defendants was managing or monitoring the work in a way that would ensure its safety.
The investigation also found that BWSC failed in its responsibility as principal contractor to ensure work was properly assessed and co-ordinated between the many contractors on site.
Shaw Group UK Ltd, of Stores Road, Derby, was fined a total of 拢17,350 and ordered to pay costs of 拢1,710 after pleading guilty to breaching Regulation 3(1) of the Management of Health and Safety at Work Regulations 1999; Regulation 8(1)(c) of the Lifting Operations and Lifting Equipment Regulations 1998; and Regulation 13(2) of the Construction (Design and Management ) Regulations 2007.
Burmeister & Wain Scandinavian Contractor, of Gydevang 35, PO Box 235, DK3450, Aller酶d, Denmark, was fined 拢4,670 and ordered to pay costs of 拢1,710 after pleading guilty to breaching Section 3(1) of the Health and Safety at Work etc Act 1974.
Burmeister & Wain Energy, of Luntoftegardsvej 93A, DK 800 Kgs Lyngby, Denmark, was fined 拢5,350 and ordered to pay costs of 拢1,710 after admitting a breach of Regulation 13(2) of the Construction (Design and Management) Regulations 2007.
HSE inspector Martin Giles said after the hearing: 鈥淭his was a large site with multiple contractors and up to 300 people working at any one time. Although there was a series of site rules set out in a construction phase plan, BWSC鈥檚 management of the site was poor as each of the main contractors ran their own areas of the site as they desired and were able to set additional rules. This led to different procedures being followed and a lack of control over temporary works.
鈥淭he failure to ensure work was carried out safely on the slope was symptomatic of more general failures which were the responsibility of聽 principal contractor BWSC in setting the rules, procedures and checks needed to manage a large site. These failures put all the workers on site at risk.
鈥淏WE specified the use of skates for installing the conveyor system but removing them required adequate risk assessment. Although the company had read the assessment and method statement produced by Shaw Group it made no comment on it and did not approve it before it was implemented. BWE should have picked up on that document鈥檚 failures and asked Shaw Group to re-evaluate before work was allowed to begin.
鈥淪haw Group UK Ltd鈥檚 risk assessment was flawed, and its management and monitoring of the task was not sufficient to identify potential problems and stop the work in the four days before Mr Doyle was hurt. The actual method of work followed by its employees was unsafe and led to Mr Doyle鈥檚 injuries when the load overturned.鈥
Got a story? Email news@theconstructionindex.co.uk