A recent decision in the Technology and Construction Court (TCC) on Toppan Holdings Limited and Abbey Healthcare (Mill Hill) Limited v Simply Construct (UK) LLP [2021] EWHC 2110 (TCC) has provided useful guidance on when a collateral warranty is a 鈥榗onstruction contract鈥 within the meaning of section 104 of the Housing, Grants, Construction and Regeneration Act 1996.
Background
Some three years after practical completion of a north London care home in 2016, fire safety defects were discovered. The freeholder, Toppan Holdings Limited, and its tenant, Abbey Healthcare (Mill Hill) Limited, requested the contractor, Simply Construct (UK) LLP, return to remedy them.
In September 2019, Toppan and Abbey employed another contractor to repair the defects that Simply had failed to carry out. Further defects were also discovered during the carrying out of the remedial works.
Toppan commenced proceedings for specific performance of the obligation under the building contract for Simply to execute a collateral warranty in favour of Abbey. In September 2020, four years after practical completion of the care home, Simply signed the collateral warranty; this warranted, among other things, that Simply 鈥渉as performed and will continue to perform diligently its obligations under the Building Contract.鈥
Toppan and Abbey both commenced adjudication proceedings against Simply in respect of their losses as a result of the remedial works. Simply argued that the collateral warranty was not a construction contract under section 104 of the Construction Act and that the adjudicator had no jurisdiction to decide the dispute.
The adjudicator issued his decision in favour of Toppan and Abbey. Simply did not pay the sums awarded in the adjudication and so Toppan and Abbey sought summary judgment to enforce the two adjudication awards in the TCC.
The legal question
The main question for the TCC to consider was whether the collateral warranty constituted a construction contract for the purposes of section 104 of the Construction Act. This was a critical point because parties to a construction contract have the implied right to refer a dispute to adjudication at any time, even in the absence of an express adjudication clause.
The decision
In finding that the collateral warranty in favour of Abbey could not be treated as a construction contract for the purposes of the Construction Act, the TCC relied on the decision in Parkwood Leisure Ltd v Laing O'Rourke Wales and West Ltd [2013], placing particular weight on Mr Justice Akenhead鈥檚 commentary that: 鈥淎 very strong pointer... will be whether or not the relevant Contractor is undertaking to the beneficiary of the warranty to carry out such operations. A pointer against may be that all the works are completed and that the Contractor is simply warrantying a past state of affairs as reaching a certain level, quality or standard鈥.
As the collateral warranty was executed four years after practical completion of the care home and the defects made good before the collateral warranty had been granted, the judge found that the collateral warranty could not be construed as an agreement for the carrying out of construction operations. As the collateral warranty was not a construction contract for the purposes of the Construction Act, there was no contractual right for Abbey to adjudicate under the Construction Act and so the decision in the Abbey adjudication was not enforced.
Practical considerations
Parties to construction disputes often prefer adjudication to court proceedings because it can provide a quick and cost-efficient resolution. If beneficiaries to collateral warranties want to ensure they have the right to adjudicate, they need to look to have the warranties executed at the earliest opportunity.
Parties to a collateral warranty may also want to consider the inclusion of a 聽dispute resolution clause which gives them the right to adjudicate under a collateral warranty, particularly where the works have already been completed.
About the author: Victoria Kempthorne is an associate solicitor in the Construction and Engineering Team at Irwin Mitchell.
Got a story? Email news@theconstructionindex.co.uk