海角社区app

海角社区app

Thu November 14 2024

Related Information

Tideway sewer hits nine-month delay

25 Aug 20 The £4bn Thames Tideway super sewer, currently under construction under London, is set to open nine months later than previously planned, the company behind the project has revealed.

The shaft at Carnwath Road with tunnel segments being delivered to TBM Rachel
The shaft at Carnwath Road with tunnel segments being delivered to TBM Rachel

Bazalgette Finance, the group of investors funding the project, say that tunnelling has been delayed by the Covid-19 lockdown and requirements for reorganising working practices.

鈥淭he company's latest modelling indicates construction work, which was due to be completed in 2024 (the project 'handover' date), is now likely to be completed in the first half of 2025, adding nine months to its current schedule,鈥 it disclosed.

The revised completion date adds 拢233m to the previous budget forecast, taking the estimated project cost to 拢4.133bn.

It added: 鈥淭ideway is in discussions with Ofwat on a package of measures that would mitigate the financial impact of COVID-19 on the company. We are making progress in these discussions and we expect to reach a full agreement in the coming months.鈥

Explaining the impact of the virus on the project, it said: 鈥淔ollowing a temporary pause of all but essential works at the start of the UK lockdown, construction work recommenced on the majority of the company's worksites in May, albeit at a lower level of activity in order to comply with social distancing requirements.鈥

Got a story? Email news@theconstructionindex.co.uk

MPU
MPU

Click here to view latest construction news »