Shorflo ensures deep piles are pumped clean

3 Aug 11 Two four-inch Super-Silent diesel pumps from Shorflo, the pump hire division of construction services specialist Groundforce, have helped during the piling for a new terminal for the Gosport to Portsmouth ferry in Hampshire.

Contractor Trant Construction hired the two 鈥渟horlfo Super鈥 pumps to de-water the three large tubular steel piles which will secure and stabilise the terminal鈥檚 new floating pontoon which is designed to ride up and down the piles so that it can rise and fall with the tides running in the Solent.

The piles, each 610mm in diameter and more than 30m in length, were driven approximately 25m into the sand and underlying clay of Portsmouth harbour before being filled with concrete to provide solid supports for the pontoon.

鈥淏efore pouring the concrete, we first had to pump out the silt and seawater from inside them,鈥 explains Trant鈥檚 site manager Mark Blackler.聽 鈥淲e chose Shorflo because we鈥檝e used them before and they are a reliable company who supply good pumps.鈥

Shorflo鈥檚 Super-Silent Betsy pumps are built around the Hidrostal screw centrifugal impeller which is renowned for its operating efficiency and its ability to handle a range of materials. With a maximum capacity of 172鲁m/hr the four-inch D100 model is exceptionally fuel efficient, consuming only 1.1litre/hr when pumping flat-out.

Related Information

At Gosport, the two pumps were supplied over two days and mounted on a barge so they could reach the piles located a few metres beyond the quay. One flooded the pile and one pumped out the sand and silt, discharging into two temporary settlement tanks mounted on the quayside. Here the silt was separated from the water which was then pumped back into the harbour.

The new 拢5 million terminal replaces the original floating pier which had reached the end of its service life. With an estimated 3.6million passengers using the facility every year, the client, Gosport Borough Council, ordered the new terminal to ensure it could cope with the steadily increasing passenger throughput.

The new pontoon was built in Deest, Holland, by specialist marine engineers Ravestein and floated down the Channel on one large barge with the pontoon being installed over one weekend .