海角社区app

海角社区app

Tue November 12 2024

Related Information

Rising to the challenge

10 Mar 20 Lateral thinking and effective use of 3D modelling software have helped contractor Kilnbridge Construction Services make a success of a small but very complex bridge contract. David Taylor reports

The east abutment was constructed above the water
The east abutment was constructed above the water

Any bridge project is 鈥 almost by definition 鈥 a challenge, if only because it involves an elevated structure spanning an inconvenient obstacle. But when east London-based contractor Kilnbridge landed the 拢5m contract to design, engineer and install the three main concrete structures for a relatively small opening bascule bridge at Canary Wharf, it could see a number or potentially challenging issues to be resolved.

Now completed, Water Street bridge provides a vehicle and pedestrian link spanning the dock between Montgomery Square and the new Wood Wharf development, a residential-led mixed-use scheme under construction by Canary Wharf Contractors.

Kilnbridge was engaged to design and engineer both east and west abutments and the marine causeway which runs alongside the existing marine deck of the new Wood Wharf development. The bridge deck, spanning 16m, is a steel structure supplied by Belgian fabricator Victor Buyck.

The west abutment comprises a number of vertical structures, including two feature columns supporting the bridge鈥檚 elastomeric bearings. The east abutment is more complicated, comprising a semi-submerged concrete structure sitting on 1.2m-diameter bored piles and housing the deck鈥檚 pivot bearing, hydraulic lifting gear and plant 谤辞辞尘.听

In addition, the east abutment is designed to withstand an impact from a small vessel.听

Under normal conditions, this abutment would have been built within a sheet-piled cofferdam. But after careful consideration, Kilnbridge chose not to do it this way: instead it decided to construct the permanent outer concrete shell above water level and then jack it down about 5m into the water.

鈥淎s a concrete contractor, we鈥檙e much happier building on dry land,鈥 says Kilnbridge鈥檚 senior engineer, Alastair Courtney. 鈥淪o we decided to do as much as possible above the water level.鈥

By effectively replacing a marine operation with a land-based one, Kilnbridge reduced the need for specialist marine plant and created a less hazardous environment for site workers.

Dispensing with the need for a sheet-piled cofferdam also had a significant practical advantage: 鈥淭he Jubilee Line runs underneath the dock and the piling work posed a risk,鈥 says Courtney. 鈥淭he cofferdam would have extended beyond the footprint of the site,鈥 he explains.

The marine piles required to support the east abutment were offset to avoid the tube line underneath.

Related Information

Kilnbridge fabricated an 18m x 12m steel platform on top of the piles to support the concrete structure and assembled a steel grillage above to act as permanent formwork. After the reinforced concrete shell had been cast and had reached final strength, it was jacked down onto the pile caps using 12 hydraulic strand jacks.

Facing a tight schedule, Kilnbridge decided that constructing some of the components in precast, rather than in-situ, concrete could听听save a lot of time. Here, the use of BIM and Tekla Structures 3D design software helped enormously, says Courtney:

鈥淏y introducing a greater amount of precast elements, we received both large time and cost savings, as well as de-risking the project as a whole. We were able to study the 3D model in detail and review both the potential advantages and constructability of changing the concrete elements to precast.听

鈥淚n addition, we were also able to ensure that the joints constructed between the precast elements would not impact on the surrounding structures,鈥 he adds.

The design software also helped solve an unexpected problem when, two weeks prior to a key element being installed, it was discovered that the original design calculations hadn鈥檛 accounted for the loadings resulting from an impact by a vessel and that changes needed to be made to the steel reinforcement.

Before being kicked down into the dock
Before being kicked down into the dock

鈥淭he required changes were all promptly incorporated within the model,鈥 says Courtney. Tekla Structures鈥 automatic clash detection confirmed the design was correct and constructible. The corresponding fabrication drawings and schedules were generated within just two days, enabling the new reinforcement to be delivered to site on time. It also allowed us to maximise re-usage of the previously ordered elements from the then obsolete design, subsequently reducing waste.鈥

Successful completion of the contract has resulted in another interesting contract with the same client: construction of a floating restaurant, which Kilnbridge is now undertaking. The floating elements will be precast at the contractor鈥檚 yard in Newham before being floated upstream.

This article was first published in the听January 2020 issue of 海角社区app Magazine

UK readers can have their own copy of the magazine, in real paper, posted through their letterbox each month by taking out an annual subscription for just 拢50 a year.听

Got a story? Email news@theconstructionindex.co.uk

MPU
MPU

Click here to view latest construction news »