The complex construction of 21 Moorfields has been further complicated by the reduction of personnel on site to meet social distancing requirements.
Developer Land Securities said: 鈥淎t 21 Moorfields, the contractor Sir Robert McAlpine, doubled the facilities space for construction workers in order to accommodate more people on site in a Covid-secure way. Weekend working was also introduced to mitigate some of the delays resulting from lower on-site capacity. However, as a result of the lower on-site capacity we now expect practical completion to be delayed to July 2022.鈥
21 Moorfields is a 17-storey steel-framed building, designed by Wilkinson Eyre, being built over the top of London鈥檚 Moorgate Crossrail station.