Purchasers of this kit housing run the risk of buying units containing 鈥榰nidentified defects鈥, according to Zoe Stollard, a partner in law firm Clarke Willmott鈥檚 construction team
She says that the UK鈥檚 standard JCT Design and Build building contract fails to provide sufficient rights for a modular housing employer to issue instructions requiring a contractor to open up for inspection.
鈥淲hile 鈥榝lat-pack鈥 homes, and modular housing generally, is a great idea, it doesn鈥檛 mean you should necessarily buy an 鈥榦ff the peg鈥 contract as well,鈥 said Ms Stollard.
鈥淭he Design and Build contract 鈥 like most other traditional building contracts 鈥 is designed for construction projects where the contractor carries out both the design and the construction work. However, off-site fabrication is a very different thing.
鈥淚t eliminates the employer鈥檚 ability to quality control at the factory during fabrication, and also the ability to check safe storage as incorrect storage solutions often contribute to defects later on.鈥
Potential faults could include external cladding that fails to meet UK-specific planning requirements or health & safety laws; or where mechanical & electrical service connections interface with the on-site elements on installation.
Last month Bristol City Council signed up to a partnership with BoKlok 鈥 a company jointly owned by Swedish retailer Ikea and construction firm Skanska 鈥 for the construction and delivery of 200 pre-fabricated modular homes.
And in June, BoKlok 鈥 which has already developed around 11,000 units in Scandinavia 鈥 agreed a deal to put up 162 鈥榝lat-pack鈥 affordable homes in Worthing; the company鈥檚 first modular properties in the UK.
鈥淥ne of the main advantages of modular builds is the materials are put together off-site,鈥 Ms Stollard acknowledged. 鈥淭his significantly reduces the on-site construction period and decreases health and safety risks normally associated with construction sites.
鈥淗owever, off-site fabrication is a very different thing and requires some careful consideration to make the project not only legally robust, but also insurable and bankable.
鈥淲ithout bespoke legal amendments that clearly express a right to inspect the construction phase taking place off-site, clients run the risk of installing pre-fabricated units which may contain unidentified defects.
鈥淓ven where the factory is run by a group company of the developer, there are still practical issues at stake where the build is not taking place on site. The designs, tests and inspections all need to be more detailed to make it work.鈥