The National Audit Office (NAO) has published its third report into HS2 but it reveals little much that has not already been made known.
It says that DfT鈥檚 latest official estimate of the cost of HS2 is between 拢65bn and 拢88bn (2015 prices), which is between 17% and 58% more than the funding that has been made available for it. 聽Other credible assessments put the likely cost at more than 拢100bn. Full services on the entire network are now forecast to start between 2036 and 2040, between three and seven years later than originally planned.
By 31st March 2019, some 拢7.4bn had already been spent on HS2.
The NAO says that HS2 Ltd, the government company tasked with getting the project built, did not adequately account for the level of uncertainty and risk in the programme when estimating the costs of Phase One (London-Birmingham) in April 2017. It used a method for calculating contingency that was not appropriate for a programme at such an early stage of development. The 拢7bn of contingency was not enough to address the huge cost increases that emerged.
Costly environmental mitigation measures were added by MPs as the Phase One enabling legislation made its passage through Parliament, including a 16km tunnel under the Chilterns. In total 拢1.2bn was added at the petitioning stage while the Phase One bill was going through parliament.
鈥淏y not fully and openly recognising the programme鈥檚 risks from the outset, DfT and HS2 Ltd have not adequately managed risks to taxpayer money,鈥 the NAO says. 鈥淭hey have tried to understand and contain costs but have been unable to bring them within the available funding, or enable passenger services to start by the planned opening date.鈥
The report concludes: 鈥淲e welcome the increased realism on the estimated cost and schedule for the programme. However, significant risks remain. While the estimated cost and schedule for Phase One are now on a stronger footing, the challenge of getting Phase One into construction, and of monitoring and managing the programme as it progresses, is considerable. Phase Two is at a far earlier stage of development with many important decisions to be made before HS2 Ltd and the Department can improve cost and schedule estimates. Completing High Speed Two will require sustained focus and support from the Department and across government to ensure the programme is re鈥慹stablished on a sound basis, balancing cost, time and benefits, and delivered in a way that achieves long-term value for money.鈥
High Speed Two: A Progress Update1 is the NAO鈥檚 third report on the project, following previousn reports in 2013 and 2016 2.
A spokesperson for HS2 Ltd said: 鈥淭he vast majority of the NAO鈥檚 findings were revealed in HS2 Ltd鈥檚 2019 stocktake 鈥 a year鈥檚 worth of deep dive investigation into the underlying costs and timescale of the project. As such, the revised costings and schedule are already widely known.
鈥淎fter being appointed HS2 Ltd CEO in 2017, Mark Thurston identified the serious challenges of complexity and risk in the project, and he made several significant changes and improvements to the organisation, its governance and processes. As the NAO recognises, this work 鈥 along with a greater understanding of the ground conditions and build requirements 鈥 means ministers have robust cost estimates for Phase One of the HS2 project. If the government decides to proceed, HS2 Ltd has a highly-skilled team in place ready to build Britain鈥檚 new state-of-the-art, low-carbon railway.鈥
- National Audit Office report, January聽 2020:
- National Audit Office report, June 2016:
National Audit Office report, May 2013: