Full cost of London Garden Bridge fiasco revealed

14 Feb 19 Transport for London has revealed that £53.5m was the total sum spent on the Garden Bridge project before it was scrapped.

The Garden Bridge vision
The Garden Bridge vision

Among the beneficiaries of the bridge that never was are the lead consulting engineer Arup, which banked 拢7.4m for services rendered.

The Bouygues Travaux Publics and Cimolai Joint Venture, which won the contract to build the bridge, was paid nearly 拢21.4m for mobilising, helping with planning and preparations and then demobilising. The nearest it came to building anything was some community gardening work.

More than 拢4.5m was spent on fundraising and promotion and press events.

Fugro got 拢1.3m for marine/ground investigation works.

The Garden Bridge project was always conceived as a visitor attraction rather than transport infrastructure, unlike most bridges. The vision was a privately operated footbridge full of trees and shrubs across the River Thames between Temple and South Bank. It was cancelled in 2017 after costs escalated beyond 拢200m. Transport for London, them under the control of London mayor Boris Johnson, and the Department for Transport had each agreed to give the project 拢30m. The rest was to come from public fundraising.

The Garden Bridge Trust, the project client, blamed the collapse of the scheme on subsequent London mayor Sadiq Khan鈥檚 refusal to underwrite the annual maintenance costs. This scared off potential donors, it said.

A report produced by Dame Margaret Hodge into the project, commissioned by Sadiq Khan, was the final nail in the coffin of the Garden Bridge. Published in April 2017, it concluded that it would be better to scrap the project at a cost of 拢46.4m to the taxpayer than to risk going ahead with it. It also confirmed that the taxpayer-funded contracts awarded to Heatherwick Studio and Arup were done so without fair and open competition.

We now know that the cost of what architect Ian Ritchie called "a wonderful exercise in celebrity hype and hubris" was even more than this. It was 拢53.5m, of which 拢43m is unrecoverable taxpayers鈥 money.

As financial administrator for the public sector funding, TfL has spent the last year reviewing the Trust's request for payment under the underwriting agreement, to ensure that the final cost from any part of the public purse is kept to a minimum.

Related Information

The review has assessed the request in detail to ensure that any payment to a third party under the agreement is fully justified.

TfL has now concluded its review and confirmed that the final amount payable to the Trust is 拢5.5m. This will come from DfT funding, and include around 拢500,000 for future liabilities and contingency associated with the formal wind-up of the Trust in accordance with Charity Commission requirements.

It is around 40% lower than it could have been, TfL said. It also means the final public sector spend will be around 拢43m - split between 拢24m from TfL and 拢19m from the DfT.

TfL has received legal advice that neither it nor the DfT have any reasonable prospect of recovering any of the money.

Alex Williams, TfL director of city planning, said: 鈥淎s part of our continuing commitment to transparency, we have published the final financial breakdown for the Garden Bridge project, on behalf of the Trust, as well as all evidence sought as part of this review.

鈥淲e worked to ensure that the cost to the public sector has been kept to a minimum, and having carefully reviewed the Garden Bridge Trust's request, we have now confirmed the final payment legally required under the terms of the underwriting agreement made by the government.

鈥淭his formally ends our involvement with the project.鈥

All documents published by TfL relating to the Garden Bridge Trust project can be found at

...celebrity hype and hubris
...celebrity hype and hubris