海角社区app

海角社区app

Sun November 03 2024

Related Information

Employer can adjudicate true value of an interim application

6 Mar 18 Is this the end of ‘smash and grab’ adjudications? Abiola Aderibigbe reports

S&T built the Premier Inn at Heathrow Terminal 4 for Grove Developments
S&T built the Premier Inn at Heathrow Terminal 4 for Grove Developments

If you fail to serve a valid payment notice or pay less notice in response to an interim application, just how big is the hole you will find yourself in?聽 That was what was at stake in the case of Grove Developments Ltd v S&T (UK) Ltd [2018] EWHC 123 (TCC) that was decided at the end of February 2018.

The Construction Act makes clear that in such circumstances the employer must pay the amount stated in the contractor鈥檚 application. Two previous decisions of the same court found that, under the standard forms generally used, the employer cannot then have an adjudicator determine the true value of the works to which the relevant interim application relates until final account stage.聽 That led to a rise in 鈥榮mash and grab鈥 adjudications where contractors claimed large sums because the employer had failed to serve valid notices, particularly late in the job where the employer would be unable to correct the position in subsequent interim payment certificates.聽 The court had held that, by failing to give notices to the contrary, the employer had agreed, or should be taken to have agreed, the amount stated in the application.

In the Grove Developments case, the court decided that its earlier decisions were wrong.聽 It found that the failure to serve a valid payment notice or pay less notice does not mean the employer has agreed to the value of the interim application or should be taken to have done so.聽 The judge noted that it was accepted that a contractor can refer to adjudication the question of the true value of the works by way of challenge to an employer鈥檚 payment notice or pay less notice. Accordingly, the prohibition of an employer commencing an adjudication to determine the true value of an interim application was contrary to the principles of 鈥榚quality and fairness鈥. He also concluded that there was nothing to justify the different treatment of interim application and final accounts, and added that this approach was supported by the Construction Act itself.聽聽聽聽聽

S&T, headquartered in Oman, was contracted by Grove Developments in March 2015 to design and build a new Premier Inn Hotel at Heathrow Terminal 4 for 拢26.4m. The contract incorporated the JCT Design and Build Contract 2011. The contractual completion date was 10th October 2016 but practical completion was not reached until 24th March 2017, leading to legal actions.

Related Information

So where does this latest ruling leave us?聽 First, if the employer fails to serve a valid notice, he will have to pay the amount in the contractor鈥檚 application (or default notice, where applicable).聽 The Grove decision does not get him out of that.聽 That could be quite a deep hole. However, it is no longer an abyss; having paid, he can then refer the proper valuation to an adjudicator to recoup any overpayment.

One area that has not been completely cleared up by the courts is precisely what is required so as to constitute a valid payment or pay less notice.聽 The Construction Act requires that the notices specify what the person considers to be due and the basis of on which it has been calculated.聽 In Grove the payless notice set out the basis of calculation, in part by reference back to the content of the payment notice without repeating that content in the pay less notice itself.聽 It was argued that the pay less notice did not therefore 鈥榮pecify鈥 the basis of calculation.聽 The adjudicator had accepted that argument.聽 鈥榃rong鈥 said the court.聽 There is nothing wrong in principle with the approach of specifying by reference to another clearly identified document.聽 The court found that the argument that the notice was invalid was 鈥渁rtificial and contrived鈥.聽 Arguments to which that label can be applied are likely to be given short shrift by the courts.

The judge, Mr Justice (Peter) Coulson, said he thought that his decision will most likely cause a reduction of 鈥榮mash and grab鈥 adjudications which, in his view, has brought adjudication into a certain amount of disrepute.聽 As this case shows, the road ahead often has many twists and turns.聽 While it is clear that the benefits of 鈥榮mash and grab鈥 adjudications have been reduced, we will have to wait and see how the future unfolds.

About the author: Abiola Aderibigbe is a paralegal in the construction and engineering team at Irwin Mitchell LLP

Got a story? Email news@theconstructionindex.co.uk

MPU

Click here to view latest construction news »