Eiffage team picked for replacement of collapsed Colombian bridge

12 Oct 18 A team of two Eiffage companies has won the contract to replace a Colombian bridge that collapsed earlier this year while under construction.

January鈥檚 collapse of the Chirajara Bridge killed 10 people.聽

Motorway concession company Coviandes has awarded Eiffage G茅nie Civil and the group's Colombian subsidiary Puentes y Torones a design-build contract for the new cable-stayed bridge at Chirajara, 100km from Bogot谩.

This 446m-long structure will have a main 286m span, supported from two V-shaped piers rising to a height of 150 m above the ravine. It forms part of a programme to modernise the motorway linking Bogot谩 and Villavicencio.

The project involves four months of preliminary studies followed by 18.5 months of construction.