Earl’s Court monster crane comes down

23 Nov 17 Specialist heavy lifting contractor ALE has begun dismantling the biggest crane in London after completing its works on the £8bn Earl’s Court project.

The AL.SK190 lifted a total of 21,016 tonnes with a total outreach change of 1,393 metres in the 195-day lifting window
The AL.SK190 lifted a total of 21,016 tonnes with a total outreach change of 1,393 metres in the 195-day lifting window

ALE has been helping Keltbray remove concrete foundations beams to clear the site of the old Earl鈥檚 Court exhibition complex. Developer Capital & Counties Properties (Capco) has a masterplan to build 8,000 new homes as well as a new High Street and a five-acre park on the site.

The Earl鈥檚 Court project is now moving to the next stages of site preparation, ahead of the construction of new homes.

ALE used its 4,300-tonne capacity AL.SK190 crane to lift out 61 portal beams, which weighed between 100 and 1,500 tonnes. The beams had supported the old exhibition halls over London Underground鈥檚 cut-and-cover District Line tracks.

The beams were lifted using the AL.SK190 between March and October overnight in 鈥榚ngineering hours鈥. During the project ALE performed what is claimed to be largest single lift undertaken in UK history by a land based crane when lifting the heaviest beam 鈥 1,500 tonnes 鈥 in just 150 minutes in June.

Having a huge crane positioned in a single location for the entire operation meant that less site space was taken up, less time was lost moving cranes around and less ground bearing pressure was placed on London Underground鈥檚 tunnels. And as the crane can operate in higher wind speeds than regular big cranes, the operational window was widened.

Related Information

ALE design engineering manager Jon Mallory said: 鈥淲e are proud to be involved in such a landmark project and provide an innovative solution to match. By choosing this crane, that could remain in one lifting position, it delivered a more favourable engineering solution that was one-of-a-kind and more cost and time-efficient.

鈥淭he effective co-operation and communication between all parties involved and the team effort all-round contributed to the successful, timely and safe completion of the project.鈥

Now the final lift has been executed, ALE is dismantling the crane.

A full report on the work of ALE and Keltbray at Earl鈥檚 Courts in the May 2017 issue of 海角社区app magazine, pages 33 to 37. It is available online at