Costain quits waste sector

21 Aug 14 Costain has decided not to bid for any more contracts in the waste sector after getting its fingers burnt in Manchester.

Pictured in 2009 are Peter Heginbotham, chairman of Viridor Laing, the JV responsible for the Greater Manchester Waste PFI contract, with Costain project director John Boyd
Pictured in 2009 are Peter Heginbotham, chairman of Viridor Laing, the JV responsible for the Greater Manchester Waste PFI contract, with Costain project director John Boyd

Costain started a 拢400m contract in 2009 to design and build a network of waste treatment facilities in Manchester for Viridor Laing. Of the 46 waste facilities to be provided under the contract, design faults have been identified at four sites, including one site that remains to be completed. The additional costs incurred here widened the operating losses in Costain鈥檚 natural resources division. 聽

鈥淓xcluding these costs the division generated an operating profit and is trading in line with expectations,鈥 the company said.

It added: "The group is not pursuing any further contracts in the waste sector."

Costain鈥檚 infrastructure division, by contrast, is performing strongly, buoying up the business as a whole.

Revenue for the six months to 30 June 2014 increased 14% to 拢529.1m (2013: 拢462.9m) and group underlying operating profit was up to 拢11.2 million (2013: 拢10.7 million).

Pre-tax profit rose 87% to 拢5.8m (2013 H1: 拢3.1m). Even stripping out exceptional items 鈥

Related Information

聽such as the 拢3.7m cost of trying and failing to acquire May Gurney last year 鈥 the adjusted profit before tax increased by 8% to 拢9.1m (2013 H1: 拢8.4m).

New business won during the first half year has pushed the order book, as at 30 June 2014, up 10% to a record 拢3.2bn (2013: 拢2.9bn). More than 拢950m of revenue has been secured for 2014, compared to 拢850m this time last year.

In the infrastructure division, revenue increased 36% to 拢358.7m (2013 H1: 拢262.8 million) while operating profit rose to 拢16.9m (2013 H1: 拢14.4m). The forward order book for the division has grown to 拢2.2bn (2013: 拢1.7bn) and the level of tendering activity remains high, the company said.

The natural resources division, which is focused on the oil & gas, nuclear process and water markets, saw its revenue shrink 15% to 拢169.4m (2013 H1: 拢199.2m) and operating loss widen to 拢2.6m (2013: 拢100,000 loss), due largely to the aforementioned Manchester waste contract.

The Manchester waste treatment network that Costain built for Viridor Laing's PFI contract includes the country鈥檚 first thermophyllic mechanical biological treatment 鈥 anaerobic digestion plant (MBT) to treat waste and produce green energy.

The 42 facilities comprise five of these MBTs in all, as well as 24 household waste recycling centres (HWRCs), four in-vessel composting (IVC) plants, one materials recovery facility (MRF), seven transfer loading stations and two green waste facilities.