A two mile section of the A30 north of Truro was due to be closed this weekend to allow a new bridge to be lifted over the road as part of Costain鈥檚 拢330m A30 Chiverton to Carland Cross upgrade.
However, Costain and its specialist lifting contractor, Ainscough Crane Hire, have recognised that the ground is not firm enough to proceed as planned. 聽They have pushed the operation back a week to the weekend of 10-13 February to allow for further work on preparing the ground. Without a solid platform, there is an unreasonable risk of the crane toppling over onto the motorway, load and all.
National Highways senior project manager Neil Winter said: 鈥淥ur contractors have detected unsuitable ground conditions for the crane deployment, and we have taken the decision to put back the bridge installation by a week to ensure everything is right for what will be a large-scale lifting operation.
鈥淎dverse weather, a mixture of heavy rainfall and low temperatures, hasn鈥檛 helped recently, these circumstances are out of our control, and the safety and effectiveness of the operation are our primary concerns.
鈥淎lthough we would have preferred to lift the bridge deck in place this coming week, we have allowed contingency in our programme, and decided to postpone to the following weekend to ensure that everything is in place ahead of the installation operation, and to give people as much notice as we can.
鈥淭he extra time will improve the ground in terms of firmer footings for the crane operation, and we鈥檙e confident a slight delay will help the teams with that, without impacting on our future road opening date.鈥
Got a story? Email news@theconstructionindex.co.uk